Updated schedule for the bwCloud-OS infrastructure migration
Created by project management bwCloud3
|
|
News
Migration of the bwCloud-OS infrastructure – new schedule
- Key-User Testphase bwCloud-OS (Gen3):
- abgeschlossen
- VM-Umzugsphase = Soft Launch bwCloud-OS (Gen3):
- Start 15.06.26
- Parallelbetrieb bwCloud-OS (Gen2/Gen3):
- 15.06.26 bis vrsstl. Mitte September 2026 – Termin wird noch bestätigt
- Abschaltung (= EOL) bwCloud-OS (Gen2):
- vrsstl. Mitte September 2026 – Termin wird noch bestätigt
- IPv4-Netzumstellung der bwCloud-OS (Gen3):
- September 2026
- Key User Testing Phase bwCloud-OS (Gen3):
- Completed
- VM Migration Phase = Soft Launch bwCloud-OS (Gen3):
- Starts June 15, 2026
- Parallel Operation bwCloud-OS (Gen2/Gen3):
- June 15, 2026 to approx. mid-September 2026 – Date to be confirmed
- Decommissioning (= EOL) bwCloud-OS (Gen2):
- Approx. mid-September 2026 – Date to be confirmed
- IPv4 Network Transition for bwCloud-OS (Gen3):
- September 2026