bwCloud-OS Generation 3: Production Phase
The bwCloud-OS Generation 3 will enter the production launch phase on September 15, 2026.
The service has already been approved for production use by eligible institutions and end users.
Until the end of November 2026, the new infrastructure will continue to be stabilized and consolidated. Starting in December 2026, bwCloud-OS Generation 3 will be available as a fully operational service.
The following image provides an overview of the individual phases and time periods.
Readiness and Migration
Institutions that have not yet achieved Gen3 Readiness by September 15, 2026, but are already preparing for it, can continue to work toward achieving readiness.
This means that the migration of end users will also remain possible after the start of the production launch phase.
During the production launch phase, the Local Support and IDM adaptations in particular will continue to be developed and optimized.
Decommissioning and “Pausing” of Resources
On September 15, 2026, the OpenStack resources will be decommissioned and shut down.
However, they will be retained until October 15, 2026, during the so-called “pausing” period to allow latecomers to complete their migration.
The office hours will be extended until October 25, 2026.
Contract Completion
Institutions that are already Gen3 Ready but whose contractual arrangements are still being finalized are asked to expedite the process and complete the contract as soon as possible.
You can contact the Coordination Office at: koordinierungsstelle@bwcloud-os.de
Further Assistance
If you require further assistance with the technical migration, please contact bwSupport: bw-support.scc.kit.edu
For further Gen3 Readiness questions, please contact the bwCloud-OS project management team: teresa.ortega@uni-mannheim.de
Important information for bwCloud-OS (Gen2) users
Existing projects on the Gen2 infrastructure can continue to be used without changes and at no additional individual cost until September 14, 2026, when they are migrated.
Instructions for migrating to Gen3 are available in the bwCloud-OS User Wiki.
Projects that have not been migrated will be shut down on the decommissioning date and “paused” until October 15, 2026. They will be deleted after that date.
Rollout Phases and Timeline
| Phase | Timeframe | Scope | Target Group | Status |
| 0 – Preparation | Jan – Apr 2026 | Hardware setup, network configuration, OpenStack deployment | Operations team, internal | completed |
| 0 – Preparation | April / May 2026 | Key user testing | Pilot users, selected projects | completed |
| 1 – Soft Launch 0 | May 15, 2026 – Jun 15, 2026 | Preparation of the production environment | Operations team, internal | completed |
| 1 – Soft Launch 1 | Jun 15, 2026 – Sep 14, 2026 | Migration of VMs/projects (standard quota flavor) | End users (institution confirmed as Gen3-ready) | completed |
| 1 – Soft Launch 2 | Jul 1, 2026 – Sep 14, 2026 | Migration of VMs/projects (custom quota flavor) | End users (institution confirmed as Gen3-ready) | completed |
| 2 – End of Gen2 Operations | Sep 15, 2026 | Shutdown | Operations team, internal | completed |
| 3 – Gen3 Production Operation | Sep 15, 2026 – Nov 30, 2026 | Production-Phase | All user groups | active |
| 3 – Gen3 Production Operation | From Dec 2026 | Full service | All user groups | planned |