Skip to main navigation Skip to main content Skip to page footer

 

Soft Launch of the bwCloud-OS Generation 3 – Period: June 15, 2026 – September 15, 2026

 

bwCloud-OS Generation 3 is currently in the soft launch phase. The service is currently available to authorized end users and institutions.

During summer 2026, the service will gradually transition into regular operation (General Availability).

 

 

bwCloud 3: Soft Launch - Roadmap

Important information for bwCloud-OS (Gen2) users

Existing projects on the Gen2 infrastructure can continue to be used without changes and at no additional cost until September 14, 2026, or until they are migrated.

Migration instructions for moving projects to Gen3 are available in the bwCloud-OS User Wiki.

Projects that have not been migrated will be deleted after September 14, 2026.

Access during the soft launch phase

Conditions

  • My home institution is confirmed as “Gen3-ready”:
  • bwCloud-OS Local Support has been appointed.
  • Local IdP adjustments have been completed.
  • I have a valid bwIDM account provided by my home institution.

     

Rollout Phases and Timeline

Phase TimeframeScopeTarget GroupStatus 
0 – PreparationJan – Apr 2026 Hardware setup, network configuration, OpenStack deploymentOperations team, internalcompleted 
0 – PreparationApril / May 2026 Key user testingPilot users, selected projectscompleted
1 – Soft Launch 0 May 15, 2026 – Jun 15, 2026Preparation of the production environmentOperations team, internalcompleted
1 – Soft Launch 1 Jun 15, 2026 – Sep 14, 2026Migration of VMs/projects (standard quota flavor)End users (institution confirmed as Gen3-ready)active
1 – Soft Launch 2  Jul 1, 2026 – Sep 14, 2026Migration of VMs/projects (custom quota flavorEnd users (institution confirmed as Gen3-ready)active
2 – End of Gen2 OperationsSep 15, 2026ShutdownOperations team, internalannounced
3 – Gen3 Production OperationSep 15, 2026 – Nov 30, 2026Stabilization phase/Consolidation phaseAll user groupsplanned
3 – Gen3 Production OperationFrom Dec 2026Full serviceAll user groupsplanned
4 – Gen2 DecommissioningSep 15, 2026 – Dec 15, 2026DecommissioningOperations team, internalplanned